Hi, I have taken over the current set up by 2 different vendors. We have only 1 Dell Blade Chassis with the set up :
- 6 Dell blades running ESXi 5.1.0 1753533 on vCenter-DC (12 Std CPU license, running 12 CPUs)
- 2 Dell blades running ESXi 5.1.0 1753533 on vCenter-VDI (50 User licenses)
- The 2 vCenters are VMs running off 2 OS in "data center" controlled by vCenter-PRD
- Each Dell blade Server has 2 CPUs
Is there a way to combine the 2x VDI blades into vCenter-DC ?
That means to make it such that vCenter-DC will have 8 Dell Blades Running ESXi 5.1.0 ?